Consultants were hiring and to date there is no technical file culminatedMOQUEGUA.- The Comptroller warned delays and risks in the hiring of consultancies to complete the technical file of the construction of the Municipal Agency of the Algarrobal district in the province of Ilo. The work is not yet begun because there is no technical file concluded and approved.
The investment project includes the construction of new infrastructure for administrative offices and citizen service, as well as their respective equipment. In 2022 it was declared viable with an amount of S/ 5 791 307 and its execution provided in 240 days (8 months). The objective is to benefit about 5,000 settlers in the Santa Rosa sector.
In the Control Milestone Report No. 5 (013-2025-OCI/ 0445-SCC), whose evaluation period was from June 11 to 17, 2025, it is noted that last year the Municipality invested S/ 113 573 in preparing the technical file of the work. However, this process stopped when they decided to change the execution modality to offer contest, a system in which a single contractor is responsible for preparing the technical file and also carrying out the construction.
Subsequently, in March 2025, a consultant for S/ 18,000 was hired to compatibilize the basic and preinversion studies approved in 2022; In addition to elaborating the terms of reference (TDR) for the new process. However, the Comptroller observed that this service was poor since the aforementioned TDRs were based on the contracting law that ceased to be in force in April 2025, so they were inapplicable.
Last June, the same provider was also hired for S/ 18,000 to implement the recommendations he had formulated in the previous service. This new service would consist in practically remakeing the pre -investment study approved since 2022, although since 2024 expenses have already been made to prepare the technical file.
These contracts delay the beginning of the work, which to date remains without a technical file culminated and approved. The adverse situation has been causing the investment project not to meet the public purpose.
The control milestone report was communicated to the head of the District Municipality of El Algarrobal to adopt the corresponding corrective actions.
For more information, visit us on our social networks:
Facebook: Comptroller Peru
Instagram: @Contraloriaperu
Twitter: @Contraloriaperu
YouTube: Comptroliatv
Tiktok: @Contraloriaperu
Flickr: Flickr.com/fotosContraloriaperu/
Moquegua, July 7, 2025
Corporate Communication Management
Press note No. 584 - 2025 -CG/GCOC