📋 Tender Overview
Project is paralyzed since 2019 and children receive classes in a borrowed place, without basic security conditionsHuanuco - The Comptroller General identified that since 2019 the improvement work of the Initial Educational Institution No. 460 is unfinished, located in the town of Alto Maranon, in the Huacrachuco district, which affects the children of the educational center that should receive classes in a premises provided by the community that does not have the basic safety conditions.
The Regional Management of Control of Huanucosuperviso the improvement project of the educational institution and found that there are unfinished works in paint, windows, locksmith and sanitary facilities. Nor have sanitary workers been installed in hygienic services and no exterior finishes have been carried out, among other items. In addition, new furniture that are stored from the paralysis of the work were found.
The project in charge of the Regional Government of Huanuco was executed with a total budget of S/ 1 657 000, which includes the execution of the work, supervision, equipment with furniture and other administrative expenses. The project was paralyzed for contract resolution reasons, and its physical advance is 70 %.
The situation that would have originated the stoppage of the project would be the construction of a retaining wall that moved due to the sliding of a slope close to construction, a situation that would have originated the suspension of the project and the subsequent contract resolution with the company.
The non -culmination of the project has caused children to continue receiving their classes in a rustic premises lent by the community, which does not meet the basic safety conditions, and they are postponed their right to receive an education in the appropriate quality conditions.
The Comptroller initiated a control service to this project, in order to determine the irregularities in its execution and find the alleged perpetrators, so that the entity corrects and guarantees its culmination for the benefit of the childhood of Alto Maranon.
Visit us at:
Twitter: @Contraloriaperu
Flickr: Flickr.com/fotosContraloriaperu/
Facebook: Comptroller Peru
Instagram: @Contraloriadelperu
YouTube: Comptroliatv
Tiktok: @Contraloriaperu
Huanuco, August 28, 2025
Corporate Communication Management
Press NOTE No. 727-2025-CG/GCOC