Comptroller Alerts Suspension Tender

📄 Tender ID: 528984211 📅 Published: 17 Feb 2026

📋 Tender Overview

- Construction projects are carried out by the National Infrastructure Authority, through the Government to Government contractAncash.- The Comptroller General of the Republic - CGR warned that the construction of Educational Institutions No. 86127 in the district of Pariacoto (Huaraz) and No. 84156 in the district of San Nicolas (Carlos Fermin Fitzcarrald) carried out by the National Infrastructure Authority (ANIN), within the framework of the Government-to-Government contract, currently remain paralyzed.

Both projects, with an updated investment of S/ 129,508,538, are part of the 12 Educational Institutions (II.EE.) that make up package 6 of the Education portfolio executed by ANIN in the regions of Ancash, Cajamarca and La Libertad, with the purpose of rebuilding the educational establishments that were affected by the El Nino Phenomenon in 2017.

According to the Concurrent Control Milestone Report No. 24385-2025-CG/MPROY-SCC, whose evaluation period extends from October 17 to November 12, 2025, the rehabilitation work of the I.E. No. 86127 of the Pariacoto district has been paralyzed since mid-November 2025, due to non-payment of appraisals and advances on the work; which has generated social conflicts. Between May and September of that same year, the contractor stopped the work, due to the same reason; which caused the lack of economic flow of the executing consortium.

The report also warned, in relation to the execution of the work, that the design of the doors in the administrative management environments of the campus does not consider windows, which does not guarantee adequate protection for the students. Likewise, the design of the kitchen does not include sanitary sub-bases, a situation that does not ensure healthy conditions for the storage, preparation and sale of food.

It should be noted that, in May 2021, the ANIN signed a contract with the consortium in charge of preparing the technical file and execution of the work whose initial budget was S/ 8,502,231; However, to date it has not been completed and said investment amount, as of November 2025, increased to S/ 59,796,912.

On the other hand, through the Concurrent Control Milestone Report No. 24409-2025-CG/MPROY-SCC, whose evaluation period also includes from October 17 to November 12, 2025, it was alerted that the rehabilitation work of the I.E. No. 84156 of the San Nicolas district shows a section of the inadequate perimeter fence adjacent to Mayta Capac Avenue, which represents a risk for passers-by and the assets of the work, considering that it has been paralyzed since April 2025.

The initial investment amount of the I.E. project. No. 84156 was S/ 9,529,765; However, as of November 2025, this figure increased to S/ 69,771,625. In both cases, the variations in the budget correspond to the incorporation of costs associated with execution, furniture and equipment, technical file, supervision, among others.

Both reports were communicated, last December, to the head of the ANIN so that he could adopt preventive and corrective measures to ensure their completion for the benefit of the students.

Ancash, February 12, 2026
Communications Management

PRESS RELEASE Ndeg 149-2026-CG/GCOM

🔍 Key Information

📄
Tender Reference No.
528984211
📅
Publication Date
17 Feb 2026
🌐
Sector
Infrastructure and construction
📝
Notice Type
News
📍
Location
Peru

📁 Documents & Downloads

No documents found

🏷️ CPV

No CPV found

Need help with this bid?

Our bid experts can help you find, evaluate & win more tenders.

🎧 Talk to Bid Expert
🕒 Submission deadline
0
days remaining · 17 Feb 2026
🔔 Set Alert

🧭 Quick Facts

Authority N/A
Country Peru
State / UT N/A
Tender Type Procurement News
Currency N/A
Similar Tenders
Loading similar tenders…