📋 Tender Overview
On October 24 the Fuchun shield tunneling machine with a diameter of 15.76 meter arrived at the receiving well after seven months of tunneling in the Fuchun River Basin. So far the Qinwang tunnel project was successfully drilled through. This is the largest shield tunnel in Zhejiang Province and the first river-crossing tunnel in the Fuchun River Basin.The Qinwang tunnel project includes two parts the river crossing and the underground comprehensive with a total length of 3066 meters connecting the north and south banks of the Fuchun River. To minimize the impact on the surrounding environment the Qinwang tunnel crossed the Fuchun River in the form of a shield tunnel. The project team optimized the design of the Fuchun shield machine during the tunneling process which ultimately ensured the successful completion of the project.Qinwang tunnel is planned to be opened to traffic in 2023 when both sides of the Fuchun River will realize three minutes to cross the river at the fastest.