Following the information made public regarding the publication of reports on Control Actions for the management of the Sustainability Fund for Tourism and the Environment Fund, carried out by the General Inspectorate of Finance, the Government clarifies the following: 1 – The phases of control action are duly delimited, such as:
The action plan is approved by the Inspector General of Finance;
This is followed by the fieldwork phase for the collection and processing of information.
Based on the information treated, the draft Report is prepared and sent to the inspected entity, aiming at the exercise of the contradictory;
After analyzing the exercise of the contradictory, the first version of the report is elaborated which, until its final version, proceeds as follows:
(i) Discussion by the Coordinator with other members of the team, allowing the Coordinator to have elements to issue his opinion;
(ii) This version, with the opinion of the Coordinator, is submitted to the Inspector General of Finance for approval.
The last phase is the approval of the report by the Member of the Government that Oversees the Finances;
Indeed, we would like to point out that, only after the approval of the Minister of Finance will we be talking about the final product of the Report. As already mentioned, in the context of enhancing transparency, all IGF Reports, since 2017, have been published immediately on the website of the Ministry of Finance, except in cases where the matter recommends that the investigation has to be deepened in other instances.
2-effectively, the General Inspection of Finance carried out control actions to the Sustainability Fund for Tourism and the Fudo do Ambiente having as scope the assessment of compliance with the applicable standards and the allocation of funding by those funds.
3- At this moment all measures are being taken, aiming at the fulfillment of the last phase of the process and that is embodied in the approval by the Minister of Finance. We expect it to be (the approval) issued over the course of next week.
With this, we would like to reinforce that the process is proceeding with the normal procedures, given its own breadth, as it encompasses funds executed by 22 municipal councils, involving a huge range of projects, under scrutiny.