📋 Tender Overview
The Bom Jardim Solar Complex, located in the municipality of Ico, in Ceara, began the testing phase of four of the 10 plants between December 2025 and January this year. The process marks progress in one of the largest solar generation projects in the Northeast of the country, strengthening the regions role in expanding renewable sources in the Brazilian energy matrix.
Part of the project portfolio of the New Acceleration and Growth Program (New PAC), the project is made up of 10 photovoltaic plants, with 706 generating units, totaling 439 megawatts (MW) of installed capacity and has an estimated investment of R2.13 billion. It is expected that all units will enter commercial operation by December 2027.
To transport the energy generated, the complex will have a transmission system of restricted interest consisting of a step-up substation and a transmission line approximately eight kilometers long to the 230 kV Substation (SE) Ico, of Companhia Hidro Eletrica do Sao Francisco (Chesf).
For an investment of this size, it is estimated that more than 20 thousand direct and indirect jobs will be created. This contributes significantly to economic and social development in the region by maintaining and creating jobs. Furthermore, the project falls under the Special Incentive Regime for Infrastructure Development (REIDI), which grants tax benefits to strategic projects for the country.
With the entry into test operation of the Bom Jardim I, II, III and V plants, the Bom Jardim Solar Complex consolidates itself as one of the main photovoltaic projects in Ceara and an important vector of the energy transition in Brazil.
Special Social Communication Advisory - MMETelephone: (61) 2032-5759 | Email: imprensa@mme.gov.br