📋 Tender Overview
* Project is executed under the Works for Taxes (OxI) mechanism.The Banco de Credito del Peru (BCP) and the Regional Government of Huancavelica officially began the execution of the works on the Expansion and improvement of the infrastructure of the Colegio La Victoria de Ayacucho project, a project that will cost more than 123 million soles and will provide this emblematic educational institution with modern environments and fully equipped with cutting-edge pedagogical technology.
After the delivery of the land on February 2 and the completion of the planning processes and updating of studies, the bank, through the RIPCONCIV Construction Company, began the first phase of the project; the construction of the contingency plan on the grounds of the San Francisco de Asis Childrens Village.
RIPCONCIV has begun topography work, excavations of retaining walls and land cuts. After that, the concrete slabs will be built on which more than 20 prefabricated classrooms, administrative areas and patios, among other complementary buildings and services, will be installed.
Until then, the more than 2,100 students from the primary, secondary and Alternative Basic Education Center (CEBA) levels will be temporarily relocated, along with teachers and administrative staff. This phase will have an estimated duration of six months.
Eng. Dante Santamaria Acosta, head of Production, and Eng. Oscar Rodriguez Morante, facilities specialist, reported that the classrooms will have special characteristics, specific to the climate of Huancavelica and, above all, they will be characterized by having thermal panels.
They explained that, according to plans, in approximately August, the students will move to the prefabricated classrooms to begin the construction of the new and modern school. They will remain in the village for approximately 16 months, the time that will be required to carry out the main work. The cost of the work will be 123 million 141 thousand 269.77 soles.
It is important to highlight that BCP, in its capacity as successful bidder and with extensive experience in the construction of similar educational infrastructures, will execute the project through the Works for Taxes (OxI) mechanism, established by Law No. 29230, which promotes regional and local public investment with the participation of the private sector.
DATA
The work includes the demolition of obsolete environments and the construction of a new educational infrastructure. Consider the complete implementation of all environments with quality furniture and equipment.