📋 Tender Overview
As a prerequisite for the renaturation of the Liesingbach, the wastewater professionals are currently building a new rainwater canal under the Liesingbach. You are currently working on a special section of this project at the southern entrance to Vienna. Where the Liesing crosses the Inzersdorf motorway node, the stream flows on a distance of 100 meters under the bridges of the eight -track Triester Strasse (B17), which flows into the A2. In addition, a bridge for the two tracks of the Badner Bahn and a pedestrian bridge with the Hermannsteg is crossed. Special attention is paid to two high -voltage lines that have to be crossed at a distance of only 25 centimeters.
That is why it is not dug open in this area, but drilled with a special machine. The rainwater canal is part of the nine-kilometer-long renaturation and flood protection project on Liesingbach, a joint project by MA45-Wiener Waters and Vienna Channel with funding from the Federal Ministry of Agriculture and Forestry, Regions and Water Management. With a diameter of 800 millimeters, the channel under the stream protects against contamination from the rainwater system in the 23rd District. The current 100 meter long section is designed as a double tube. Using the latest tunnel boring technology, a borehole and reinforced concrete protective tube with 1,500 millimeters of outside diameter (1,200 millimeters inner diameter) are driven under the bridges. The 800 millimeter (inside diameter) sewage pipe made of fiber optic reinforced plastic is later drawn into this pipe. Depending on the nature of the soil, the water professionals calculate 15 to 20 meters in the underground every day. District head Gerald Bischof: The channel professionals do great things here! The channel is the basis for the project because it ensures a clean stream. The renaturation afterwards brings a high -quality habitat for flora and fauna and thus an attractive local recreation room for all of us!
The machine used is a closed full -cut machine with hydraulic support cycle. The upcoming floor is removed with a drill head adapted to geology, crushed and liquefied with a bentonite, a mixture of different sound minerals. This suspension is encouraged via pressure hoses to the surface and separated into liquid and solids via sieves and cyclones. The drilling fluid is brought back into the dismantling circuit and pumped back to the drilling head. The self -contained circulation ensures a minimization of additional disposal paths. What remains is the dismantled earth material from the tunnel. However, the suspension not only takes over the transport and lubrication function, but also with a compressed air cushion also the support function on the local breast, the foremost mining site in the tunnel. At the same time as the dismantling of the earth material, four presses and a pressure of 500 bar are pushed into the surface of the meter long and 4.6 tons of reinforced concrete. In total, 33 of these pipes with a total weight of 152 tons must be installed in total. Technology fans can get into enthusiasm, Viennas channel building manager Marlies Greussing is enthusiastic. The 3.75 meter long and 13 -ton drilling head used crushes the ground on the drilling head with six revolutions per minute (rpm) and 258 kilonewton meters (KNM). This corresponds to the power of approx. 5,000 commercially available drilling machines.
The pipe bundle route starts as a precisely 10 meter length followed by a 90 -meter -long right -hand bend with a radius of 500 meters. The entire route has a slope of 2.8 per thousand (2.8 mm per m). Due to the curvature of the route, no direct visual contact from the starting pit to the propulsion machine is possible. In order not to damage the bridge foundations and high -voltage lines during this three -dimensional cornering, and the goal of reaching 100 meters away is particularly important on the measurement system. An electronic hose scale and a roundabout compass (gyroscope) enable the precise alignment of the drilling head. The hose scale measures the fluid level in two places via pressure sensors that are connected to each other with a hose. It determines the vertical position of the machine. The roundabout compass (Nordsuche) can continuously determine the horizontal location without measuring breaks during the propulsion. Such sensors can also determine the rotary and pine movement of a missile, even if the GPS fails, Greussing explains the precision of measurement. Both values are calculated depending on the planned propulsion axis and the exact position of the tunneling machine is constantly determined. With a total of 30 kilometers, the Liesingbach is the longest Wienerwaldbach. By 2027, the waters will be dismantled by the Viennese waters department as part of the large project Integrative Flood Protection Liesingbach over a length of 9.2 kilometers.
In the course of this, around 9 kilometers of channel are built by Vienna Canal, 5.5 kilometers of which are laid in the stream bed. For operation and maintenance, 16 separation buildings, 7 waste shafts and 29 plaster shafts are built along the route. The rainwater channels that previously culminated into the Liesing are connected to the new channel. In the event of rain, the first gush with contaminated rainwater can be intercepted from the surrounding traffic areas in the new channel and guided to the sewage treatment plant in Simmering for cleaning. In the future, the new channel will also secure accidents where dangerous substances could get into the stream via the rainwater sewer system. This improves water quality. Particularly environmentally friendly: the old paving stones are crushed on site and brought into the sole of the Liesingbach. This recycling replaces the elaborate removal of the stones and the associated truck journeys. The total costs of the large project including the construction of the Gelbe Haide memory basin amount to around 83 million.