Bridges and Tunnels

Austria Despite Flooding Tender

📄 Tender ID: 508669498 📅 Published: 25 Sep 2024

📋 Tender Overview

For the new rainwater canal under the Liesingbach, Marlies, the tunnel boring machine from Wien Kanal, reached its destination after eight days. It dug for 132 hours for the 100-meter-long stretch. However, the work was interrupted by the flood.

As expected, the two high-voltage lines, only 25 centimeters apart, posed a particular challenge. The tunnel builders were very well prepared for the rain of the century from September 13th to 16th. Emergency plans for a flood in the Liesingbach were developed even before construction began. Necessary equipment and sealing materials were kept ready at the starting shaft for the expected emergency.

When the alarm level in the Liesingbach was reached, the tunnel boring work was stopped on Saturday, September 14th, 2024, at 6 p.m. due to the acute flood situation. The construction site was immediately secured and a watertight seal was built around the tunnel tube. This protected the boring machine for the time being. But the water in the Liesingbach continued to rise.

On Sunday, September 15, 2024, at 3 a.m., the starting pit was flooded in a controlled manner. The starting shaft and the 83-meter-long tunnel that had already been drilled with the machine enclosed now had to withstand a water column of 7.5 meters. The controlled flooding prevented damage to the starting pit, the tunnel and the tunneling machine. As the rain subsided, the construction site was able to be drained on Monday, September 16, 2024, so that drilling work could be resumed the following day.

The drilling team needed another 33 hours for the last 24 meters to the end of the tunnel.
With a total length of 30 kilometers, the Liesingbach is the longest stream in the Vienna Woods. By 2027, the MA45 will have restored the watercourse to a natural state over a length of 9 kilometers. As a preliminary work, Wien Kanal is building a 9-kilometer-long rainwater canal, 5.5 kilometers of which run directly under the stream bed. For operation and maintenance, 16 separation structures, 7 waste shafts and 29 cleaning shafts will be built along the route.
The rainwater canals, which previously all flowed into the Liesing, will be connected to the new canal. When it rains, the first surge of contaminated rainwater from the surrounding traffic areas can be intercepted in the new canal and channeled to the sewage treatment plant in Simmering for cleaning. The new canal will also protect against incidents in which dangerous substances could enter the stream via the rainwater sewer system. This improves the water quality.

Particularly environmentally friendly: the old paving stones will be crushed on site and placed in the bed of the Liesing stream. This recycling replaces the time-consuming removal of the stones and the associated truck journeys. The total cost of the major project, including the construction of the Gelbe Haide reservoir, is around 83 million. The City of Viennas share of the entire project is around 65 million euros. The entire project is funded by the Federal Ministry of Agriculture, Forestry, Regions and Water Management with around 18 million euros. The B.A.C.H.L. information center shows interesting details about the major project. The employees of the Vienna Waters and Vienna Canal department keep you up to date on the progress of the renaturation work every first Friday of the month from 2 p.m. to 6 p.m. The information center is located in the 23rd district at Gutheil-Schoder-Gasse 19.

With a pipeline length of more than 2,500 kilometers, Vienna Canal is Austrias largest sewer network operator. Every day, around half a billion liters of wastewater from 2 million people and 180,000 buildings are transported safely and in an environmentally friendly manner to the sewage treatment plant in Simmering. Around 450 employees keep the sewer network functional and clean. Last year, 15 tons of deposited material were cleared from the sewers every day to guarantee the flow to the sewage treatment plant. 99.8 percent of all households in Vienna are connected to the citys sewer network. Nevertheless, Viennas sewer network grew by 2 kilometers in 2023 and over 1,600 sewer construction sites were carried out to maintain and repair the public sewer network. 900 manhole covers were replaced and 8 kilometers of sewers were renovated or rebuilt. Most of them are underground, so almost no excavation is required. The robots from Vienna Kanal also operate underground. Last year alone, they covered 250 kilometers in the sewage labyrinth and examined the pipes for damage.

🔍 Key Information

📄
Tender Reference No.
508669498
📅
Publication Date
25 Sep 2024
🌐
Sector
Bridges and Tunnels
📝
Notice Type
News
📍
Location
Austria

📁 Documents & Downloads

No documents found

🏷️ CPV

No CPV found

Need help with this bid?

Our bid experts can help you find, evaluate & win more tenders.

🎧 Talk to Bid Expert
🕒 Submission deadline
0
days remaining · 25 Sep 2024
🔔 Set Alert

🧭 Quick Facts

Authority N/A
Country Austria
State / UT N/A
Tender Type Procurement News
Currency N/A
Similar Tenders
Loading similar tenders…