📋 Tender Overview
After intense work by crews from the 23rd District of Santa Cruz and the 13th District of Chubut, the National Highway Authority completed the repair of the undermining in the road area of km 1,860 of National Route 3, at the height of the sector called "Punta Peligro".
The action plan coordinated by the engineers and technicians of the road agency made it possible to resolve during this weekend the gullies that were recorded during the past week, after several days of rainfall in the area.
With the work of the heavy road machinery of both districts, the tasks consisted of the execution of soil movement, the contribution of 750 cubic meters of granular material to fill the gullies in the road area and later the restoration of the affected land to recover normal conditions in the indicated section.
In addition, in the evaluation carried out by the engineers, other smaller gullies were detected in a nearby sector, which were also filled with granular material to prevent erosion.
Although this sinkhole caused by the rain has already been solved, in the coming days road personnel will continue to work on the cleaning and readaptation of the ditch area of this section of RN 3 to avoid future inconveniences with the rains that are usually generated at this time of year.
It should be noted that this sector of National Route 3 will be disaffected from the national road network when the construction of the bypass progresses as part of the work to transform it into a highway between Caleta Olivia and Rada Tilly.
National Roads asks users to circulate with caution at the height of Km 1,860 of the aforementioned corridor, as well as to respect the existing signage and the indications of the personnel who will continue to work in the area during this week.