📋 Tender Overview
The installation of LED lighting, added to the construction of the new roundabout access to that town, completed the work that will improve road safety conditions in this area of National Route 25.
Through the installation of a modern LED lighting system, the National Highway Authority completed the last stage of the work, which consisted mainly of the construction of a new roundabout to access the town of Dolavon, at Km 56 of National Route 25.
The works consisted of the placement of 67 12-meter-high columns with LED luminaires, underground power lines, main panel and a transformer for power supply within the system.
The completed tasks were part of the work to readapt the access to Dolavon, which consisted of the construction of a roundabout to channel the entrances and exits to that town from National Route 25 and thus improve the conditions of trafficability, accessibility and safety of users.
For the readaptation of the access, the soil movement was first completed according to the new design and a draining sub-base and an antifreeze base were executed. Subsequently, a league irrigation and the construction of the asphalt layer were carried out.
Likewise, the existing branches and the sector of National Route 25 that make up the intersection were repaved with a folder of hot bituminous material. In addition, roadway repair work was carried out beforehand.
At the same time, gravel shoulders were built and the existing ones were readapted, contemplating the construction of a high emergent cordon and two culverts. Finally, the vertical marking and the definitive horizontal demarcation were carried out.
The lighting of the new access to the town of Dolavon will provide greater security to those who circulate through that sector, entering the town of Las Norias, and to those people who continue traveling along National Route 25 towards the mountain range or towards the coast of the province.