📋 Tender Overview
The existing Napajedla marina is no longer sufficient in capacity for the growing interest in recreational boating and tourism on the Bata Canal which is why it is being expanded nearly twofold. The construction will smoothly connect to the existing marina edge and offer more space for the safe longitudinal mooring of vessels for visitors to the city from the waterway. The opening is planned for this summer season.
The Napajedla marina is located in the reservoir of the Spytihnev weir on the left bank of the Morava River near the city center. In its current form it was built by the Directorate of Waterways of the Czech Republic during the first wave of public marina infrastructure development on the Bata Canal in the Zlin Region in 2008-2009 and was inaugurated by Tomas Bata Jr. opening the city to tourism on the waterway. However it is now insufficient for the growing traffic of recreational vessels and the dynamic development of tourism in the region.
The expansion of the marina is another step to keep pace with the growing interest in recreation on the Bata Canal and to provide visitors and locals with the highest possible comfort and safety when visiting the city of Napajedla says Lubomir Fojtu director of the Directorate of Waterways of the Czech Republic adding: The new capacity of the marina will allow for smoother operations and better accessibility to the city from the waterway which will contribute to further tourism development in the entire region. The marina is operated by the waterway manager the Morava River Basin.
The newly initiated construction technically connects to the existing solid marina edge of 45 meters in length which will be extended by 40 meters to a total of 85 meters. Construction work will take place at both ends of the current pier. On the southern side of the existing marina a new 20-meter-long pier with a width of 3 meters will be built. Subsequently another 20 meters of pier with a width of 7 meters will be constructed on the northern side of the marina. The dominant feature of the new parts of the marina will be high seating steps that will follow the existing terrain of the sloping bank. The seating steps 47 cm high will be connected to a new access staircase. The steps will consist of variously wide prefabricated pieces. The upper row of seating steps will feature the inscription NAPAJEDLA. In the area of the new marina edge dredging of the riverbed will also be carried out to ensure a minimum navigation depth of 1.5 meters and the riverbed will be reinforced with rubble stone. New mooring elements will be installed on the new marina edge for securing vessels.
Construction work will proceed gradually. First a sheet pile wall will be built followed by concrete pouring installation of concrete prefabricates and finally the installation of new mooring elements for vessels says Vladimir Dvorak director of the company Engineering and Transport Construction Olomouc a.s. the contractor for the construction.
The expansion of the marina is significant news for Napajedla - it responds to the needs of our visitors and residents and strengthens the connection between the city and the Bata Canal says Robert Podlas mayor of the city of Napajedla. During the construction there will be temporary restrictions on the bike path which will be coordinated with the investor and the construction company to minimize the impact on public movement around the construction site.
Short-term closures of the bike path will only occur during more demanding construction work such as concrete pouring or the movement of materials and machinery and the driving of sheet piles which could endanger pedestrians and cyclists. For such cases a detour route of 400 meters will be marked to divert traffic to a side street.
The contractor for the construction is IDS - Engineering and Transport Construction Olomouc a.s. The costs of 15.8 million CZK excluding VAT are financed by the State Fund for Transport Infrastructure.
Historical Context
The first wave of building public marinas on the Bata Canal in the Zlin Region took place from 2007 to 2010. When the Bata Canal waterway was built the landing site in Napajedla was not considered at all. Boats only passed through with a cargo of lignite to Otrokovice. After the resumption of navigation in 1995 the possibility of reliably mooring vessels allowing safe disembarkation and embarkation of people was very limited. Due to the absence of marinas direct access from the waterway to many interesting and attractive destinations for visitors was thus prevented and the marina in Napajedla was increasingly missed.
Later the marina was also equipped with electrical and water connections for boats similar to other marinas to make mooring during the journey along the waterway as comfortable as possible. The development of tourism and the growing popularity of the Bata Canal however shows the need for further adjustments to some marinas which are no longer sufficient for the increasing number of boats and tourists.
About the Directorate of Waterways of the Czech Republic
The Directorate of Waterways of the Czech Republic is an organizational unit of the state established by the Ministry of Transport to ensure the preparation and implementation of the construction and modernization of transport-significant utilized waterways and other structures necessary for operations on waterways. The Directorate of Waterways of the Czech Republic also operates public ports and marinas as well as the tugboat BESKYDY.