📋 Tender Overview
- The Comptrollers Office alerted the commune that there are construction deficiencies and unfinished items so that it can adopt corrective measures.Apurimac.- The Comptroller General of the Republic alerted the Provincial Municipality of Antabamba about construction deficiencies and unfinished items in the execution of the work of the drinking water and basic sanitation system of the district and province of Antabamba, a situation that puts at risk the useful life of the infrastructure, its correct functioning and the timely delivery of the service in favor of citizens.
The work to improve and expand the drinking water and basic sanitation system being carried out in the communities of Curanco, Ccocho, Chunohuacho, Mollocco, Ccolpa and Tatapampa, with a budget of S/ 12,032,312, aims to contribute to reducing cases of gastrointestinal, parasitic and skin diseases in the population.
In the Control Milestone Report No. 006-2026-OCI/0350-SCC (period from February 2 to 20, 2026) it is detailed that by mayoral resolution of October 2025, the work reception committee was formed. However, there are situations to be solved, such as, for example, in the collection and conduction line where there are foundations of exposed and unsupported perimeter fences, as well as out-of-square chamber covers that generate a risk of water contamination.
In addition to the delay in receiving the work and the failure to collect observations, they could lead to non-compliance by the contractor, as well as the non-application of penalties by the entity.
Likewise, installations of pipes without anchors and/or provisional were verified, as well as water leaks, in addition to pipes exposed to the elements; while, in the treatment plant, the lack of cleaning and an adequate water drainage system was evident.
In the Basic Sanitation Units (UBS), the settlement of sidewalks, clogged percolator wells, broken drainage boxes, exposed drainage pipes, separation between the laundry rooms and the walls of the units were observed. The existence of unfinished electrical installations was also identified, in addition to sectors that still lack water supply, to which is added the lack of finishes such as paint on metal doors, etc.
Closed sanitary micro-landfills were also noted that were not completed according to the technical specifications of the file, omitting the final treatment and revegetation, which could become an infectious focus for the surrounding communities.
The control report was notified to the mayor of the Provincial Municipality of Antabamba so that he can adopt the necessary preventive and corrective actions. This document is available in the Control Service Report Search.
Apurimac, March 9, 2026
Communications Management
PRESS RELEASE Ndeg 237-2026-CG/GCOM