📋 Tender Overview
General plan schedule includes 6 objectives oriented to the treatment and regulation of the river river and the drainage systems of the Piura, Castilla, twenty -six of October and Catacaos districts.The National Infrastructure Authority (ANIN), through the Directorate of Studies and Works, led the fourth session of the Technical Coordination Commission (CTC) of the Integral Flood Control Project of the Piura River Basin and a storm drainage of Piura, Castilla, October twenty -six and Catacaos, held at the Faculty of Civil Engineering of the National University of Piura.
During the day, the Anin technical team presented the advances achieved in the four components of the plan: natural infrastructure, rain drainage, flood control and rapid interventions. Within the framework of the rain drainage component, a report will be issued with the diagnosis of the evaluations made to the Sares and the advantages and disadvantages of its use and applicability will be detailed.
It should be noted that, the schedule of the General Flood Control Project Plan includes 6 objectives aimed at the treatment and regulation of the Piura River and the drainage systems of the Piura, Castilla districts, October twenty -six and Catacaos: determination of the threshold flow, location of feasible reservoirs, determination of basins, determination of hydraulic capacity of drains and formulation of the pre -investment study at the level of flood control profile and rain drainage preinversion profile.
In objective 1 (determination of the threshold flow) records an advance of 62.6 %, while objective 2 (location of feasible reservoirs) has an advance of 18.65 %. With the advances obtained to date it is expected to start with the elaboration of the profile at the beginning of August 2025, giving way to objective 3 (pre -investment profile of flood control).
Regarding objective 4, 68% progress is recorded for the determination of basins and microbasins. In addition, 100% geology works were completed and hydrological modeling works have begun. It is planned to culminate by the end of June.
As part of the actions of the fast interventions plan, a key strategy to protect vulnerable communities, on May 20 the construction of riverside defenses began in the Chanrro and Piedra Azul hamlets, in San Miguel de El Faique, whose investment is exceeding 11 million soles.
During the CTC, key agreements were generated and the ANIN specialists collected the contributions provided by the technical specialists accredited from the various institutions that actively participate in this commission. These contributions strengthen the technical approach of the project and allow a joint and participatory construction of the comprehensive profile.
Representatives of the ANIN, Water Resources Council of Cuenca Chira Piura, Senamhi, College of Economists of Peru, College of Journalists of Peru, National University of Piura; In addition to officials from the municipalities of Piura, Castilla, Catacaos, October twenty-six, and Morropon-Chulucanas, among other civil society groups. The next CTC meeting will take place on June 26, 2025.
With this project, the Executive Power, through the ANIN, ratifies its commitment to the reduction of disasters risk in favor of populations in vulnerable situations throughout the country, since it is also executing more works of this type in other regions of the country.