📄 Tender ID: 519091161 📅 Published: 13 Jun 2025

📋 Tender Overview

Colegio Capullitos de Rosa Rehabilitation continues in arbitration, affecting about 200 studentsLambayeque. -The Comptroller General of the Republic -CGR warned that the Provincial Municipality of Chiclayo (MPCH) approved and paid for work not executed or unfinished in the Initial Educational Institution (I.E.I.) No. 044 Rose Capullitos as verified in a recent inspection to the aforementioned Center for Studies, whose rehabilitation work is paralyzed for more than 500 days and has been affecting about 200 students.

The Control Milestone Report No. 027-2025-OCI/0425-SCC, which evaluated the period from May 19 to 23, 2025, revealed that the MPCH authorized the payment of six works of work execution, however, during the inspection carried out by the Control Commission, items were found that were not executed or were unfinished.

Among the works questioned, items reported as culminated in the valuation No. 6 but that in the field had not been completed, such as the construction of the high tank, walls and partitions of masonry, tarrajeo, tarrajeo, coatings and sanitary installations, were identified in the field. Even, in the case of porcelain placement, paths, patio and paint slab, no evidence of execution was found, despite appearing with advances of up to 100%.

The Comptroller said that it corresponds to the mayor to verify the real advances during the technical-financial settlement of the contract. In addition, he recalled that the consulting contract included clauses that contemplate penalties for the valorization and payment of metrades not executed.

Regarding the social impact of the delay, the nearly 200 students of the initial level continue to be displaced in a provisional place - La I.E. Antonio Jose de Sucre - that does not have the security conditions or adaptation to develop classes, a situation that puts at risk its physical integrity and compliance with the educational purpose of the project. It was noted that the mayor does not adopt the necessary actions to improve such conditions.

It should be noted that the contract for the rehabilitation of the infrastructure of the I.E.I. Capullitos de Rosa was signed in June 2021 between the MPCH and a consortium for S/ 2 433 550, with a period of 120 days. But, after six term suspensions, it was resolved in 2023 by both parties, under different arguments: the company alleged lack of response to consultations and absence of supervisor; while the MPCH argued an advance of less than 80% by the contractor.

Until today, the Municipality has paid a total of S/ 1 593 716 between the valuation of the main contract and an additional benefit. The work should culminate November 21, 2021, but the accumulated physical progress barely reaches 58.56% compared to 89.77% scheduled, evidencing a 31.21% delay in execution.

The report was communicated to the head of the MPCH for the corresponding actions that ensure the continuity and correct culmination of the project. The full report is available in the institutional portal: www.contraloria.gob.pe.

Visit us at:

X: @Contraloriaperu
Flickr: Flickr.com/fotosContraloriaperu/
Facebook: Comptroller Peru
Instagram: @Contraloriadelperu
YouTube: Comptroliatv
Tiktok: @Contraloriaperu

Lambayeque, June 11, 2025
Corporate Communication Management

Press note No. 502-2025-CG/GCOC

🔍 Key Information

📄
Tender Reference No.
519091161
📅
Publication Date
13 Jun 2025
🌐
Sector
Infrastructure and construction
📝
Notice Type
News
📍
Location
Peru

📁 Documents & Downloads

No documents found

🏷️ CPV

No CPV found

Need help with this bid?

Our bid experts can help you find, evaluate & win more tenders.

🎧 Talk to Bid Expert
🕒 Submission deadline
0
days remaining · 13 Jun 2025
🔔 Set Alert

🧭 Quick Facts

Authority N/A
Country Peru
State / UT N/A
Tender Type Procurement News
Currency N/A
Similar Tenders
Loading similar tenders…